Monday, February 10, 2014

LOT 3 WADDI ROAD AND LOT 301 YANDIN ROAD

9.4.3 WIND PROSPECT WA PTY LTD – PROPOSED RENEWAL AND  EXTENSION TO APPROVAL FOR WIND MONITORING  TOWERS – LOT 3 WADDI ROAD AND LOT 301 YANDIN ROAD, 
DANDARAGAN
Location: Lot 3 Waddi Road and Lot 301 Yandin Road, Dandaragan
Applicant: Wind Prospect WA Pty Ltd on behalf of Mr G Creagh  and Mr P W Shields
Folder path: Development Services App / Development
Application / 2011 / 14 & 15
Disclosure of interest: None
Date: 11 July 2014
Author: David Chidlow, Manager Planning
Signature of Author:

PROPOSAL
To consider an application from Wind Prospect WA Pty Ltd on behalf of Mr G Creagh and Mr P Shields to extend planning approval for two temporary wind monitoring towers, one located on Lot 3 and a second on Lot 301.
BACKGROUND
Council granted planning approval to Wind Prospect WA Pty Ltd on behalf of Mr G Creagh and Mr P Shields, for the erection of two wind monitoring towers, one to be located on Lot 3 Waddi Rd and the second to be located on Lot 301 Yandin Rd, Dandaragan, in March 2008
These wind monitoring towers were subsequently constructed on 10 May 2008 and 15 May 2008 respectively.
Delays in commencing construction of the wind farms has meant that the towers have remained in place.
Wind Prospect WA Pty Ltd requests an extension to this Planning Approval to align the period of time in which these two wind monitoring towers can remain in place with the Planning Approval for the Waddi Wind Farm and Yandin Wind Farm granted at the December 2011 Council meeting.
COMMENT
The intention is that the relevant wind monitoring towers would remain in place until construction commences at each wind farm at which time the relevant wind monitoring tower would be removed.
The timing of commencement of construction of each wind farm is currently uncertain however the permit for each wind farm requires that the development must be substantially commenced within 4 years. (January 2016)
It is therefore requested that an extension is provided to the period of time in which the two wind monitoring towers can remain in 33 place to be such that the relevant wind monitoring tower must be removed within 3 months of construction commencing at the corresponding wind farm or upon expiry of the relevant wind farm planning permit. This would enable the wind monitoring towers to remain in place if an extension to the Planning Approval for one or both of the wind farms is sought and granted
CONSULTATION
Nil
STATUTORY ENVIRONMENT
 Local Planning Scheme No 7
POLICY IMPLICATIONS
There are no policy implications relevant to this item.
FINANCIAL IMPLICATIONS
There are no financial implications relevant to this item.
STRATEGIC IMPLICATIONS
There are no strategic implications relevant to this item.
ATTACHMENTS
Circulated with the agenda is the following item relevant to this report:
Submission from Wind Prospect WA Pty Ltd (Doc Id: 24862)
(Marked 9.4.3)
VOTING REQUIREMENT
Simple majority
OFFICER RECOMMENDATION

That planning approval previously granted to Wind Prospect WA Pty Ltd on behalf of Mr G Creagh and Mr P Shields for temporary wind monitoring towers one on Lot 3 Waddi Road and the second on Lot 301 Yandin Road, Dandaragan be renewed and extended until 11 January 2016 subject to the temporary wind towers being removed within 3 months of the commencement of construction of the relevant wind farm.